Roscommon Update
25th March 2008 - 11 weeks ago - all of the green complexes are
shaped, drained, gravel and rootzone in place and now topsoil applied to the surrounds of 4 no. greens - 3rd, 10th, 16th & 17th.
Our 15 week timescale is a little ahead of schedule and hopefully
It was encouraging to see the "finishing" equipment arriving on
site today i.e. Harrows, leveling bars, seeders etc..
The seeding of the greens will start this week.