Golf Links Road, Roscommon, Ireland.   
t. +353 9066 28883   m. +353 87 2041922   e. info@kearneygolfdesign.com

Tuesday 10 February 2009

Bunker remodel underway at Grange GC

Following a comprehensive audit of the bunker complexes at Grange GC late last year, a full remodel of all bunkers is underway. The remodel will incorporate the original James Braid design and by marrying new techniques ie aquadyne drainage with the old design, this remodel will bring the original strategy and historical design concepts back to life. Progress can be monitored on the large presentation board in the clubhouse

2 Green remodel almost complete at Birr GC





The two hole remodel at Birr GC is almost complete. The sodding at 12th green is finished and works are almost done at the newly remodeled 7th green also. Note from the photos that the staff have fenced off the greens to keep the deer off the newly sodded areas.






The strip area at the 7th green complex was over 5,000 sq.m. and the entirety of the area has been capped with sand. Once the sod has established the bunkers will be shelled out and the new sand placed.